DATA SHEET FOR THE PROJECT EQUIPMENT FOR THE OPERATION OF LOADING AND UNLOADING SHIPS DEPOT OF ABIDJAN

Order No.

ITEM

DESCRIPTION

1

Object

Develop and strengthen the export activities of Oil Products

Acquire new partners

Increase the financial resources.

2

Background

Increased storage capacity

Increased volumes of exported products

Increased pumping capacity

Recognition of commodities.

Technical Specifications

A network of steel tube pipe API 5LGRD, SCH40, Ø 12'' length = 15000 ml

Three (3) tanks of 32 000 m3 each 

That is : 96 000 m3 in total :

        1 tank JET A1 (kerosene)

        1 tank Premium (SSP)

        1 tank Diesel (GO)

Three (3) power pumps :  stream flow = 750 m3/H - HMT =  85m - NPSH = 5 m

Two (2) Generators of 1600 KVA each

Three (3) ultrasonic flow meters

4

Sponsor

GESTOCI

5

Investment

35 million EURO

46 million USD

6

Status

Initial studies detailed project completed

7

Need for Partners

Need for financial partners for the construction

8

Contact 

GESTOCI 15 BP 89 ABIDJAN 15, Boulevard de VRIDI, CÔTE D'IVOIRE

Félix  BONGBA

Tel : (225) 21 75 98 00 / E-mail : fbongba@gestoci.ci /
                   21 75 98 18